Tuesday, May 15, 2012

Form Boards!

Yesterday after working in 80 degree heat I finally finished forming up for the slab.  After running string lines, squaring up and leveling, the form boards are now in place, but this is only the beginning of the foundation process.  I have to add plumbing, vapor barrier, 2 inch high density styro-foam, wire mesh, dig out and add re-bar for the grade beam and layout PEX tube for the in floor heat.  And finally the cement itself!  Also before the cement I will need to add more fill around the perimeter of the foundation to strengthen up the sand from washing out from rain.

No comments:

Post a Comment