Wednesday, November 18, 2009

More Plumbing







Well, the weather has finally cleared up and things are drying out, the problem now though is the old weather has arrived and with it frost. My fiance and I went out to the property and finished the in ground plumbing that i have put on hold until now due to the extreme amounts of rain we have had since the last time I worked on it. First off, the ground already has a few inches of frost in it and so digging was hard, but other than that we had some beautiful late fall weather, the thermometer getting up to almost 50 degrees!


I already had the trenches for the drains dug (thankfully!) and the fittings in place. All we had to do was cut the pipe to the right lengths and test fit. Once the test fitting was done, I used a marker and marked each connection so I was able to remove the pipe. Next came purple prime and glue. I wont say the whole process was quick- I rechecked alot of my angles and runs many times. My fiance questioned why I was doing so and I told her that it was better to measure many times and make one cut. I also wanted to make sure it would work, because once the cement is poured, there will be no access to fix it without cutting thru cement and pex lines!


Needless to say, by the end of the day we had the drain lines in, glued and covered with sand. I think we both went away with the feeling of accomplishment. All I have left is to get a few hay bales and fluff some hay over the lines to prevent the frost from going down to deep and upsetting the pipes and also replace the plastic bags we used as temporary caps on the open pipes with real caps. This will keep water from entering the system and sitting in the lines and freezing. Snow is expected anytime now, so I think construction is on hold now till the spring thaw.

Sunday, November 8, 2009

Plumbing


Before the slab can be poured, the underground plumbing for the drains must be installed. This of course relies on some good ol' muscle and brain power. The muscle is for digging the trenches that the pipe must be laid in, the brain power is for properly dedeucing the correct flow of waste water and the correct angle of the pipe (remember water runs down hill, not up).


Fortunately I have planned to place the bathrooms and utility room in the same room, so that helps alot with the amount of trenching that is needed. Not only that, the upstairs half bath will be directly above this room, so everything is nicely stacked. The only long trench that was needed was the one for the kitchen sink, which by its nature is in the kitchen and not the bathroom.


So far it has gone well. For once we had a few nice days of warmer dry weather so that when I finally had a chance to go out to the property and figure out the lay of the pipes I did not have to wade through muck. I still dont think I will have the opportunity to pour the slab yet, but if I can at least get this plumbing done I can cap the pipes and lay hay on what I have done and wait for the warm spring breeze to grace this land once again.